Paper Title:
Field Monitoring and Analysis of Envelope Pile in Shijiazhuang Six-Line Tunnel
  Abstract

The length of Shijiazhuang Railway six-line tunnel(Beijing-Shijiazhuang Passenger line) is 4980m, cut and cover excavation method is used widely. The width of pit is 30~52m and the depth is 8.5~22m. In order to use large machine, cable support structure is used. The west side of pit is Beijing-Guangzhou Railway. The nearest distance from pit is only 10.2m. The cable properties will change because of the train vibration. Therefore, the scope of the train vibration, vibration velocity, anchor axial force and horizontal displacement of pile are measured to get the influence of the train vibration, which can provide basic data for design and construction.

  Info
Periodical
Edited by
Xuejun Zhou
Pages
1791-1794
DOI
10.4028/www.scientific.net/AMM.90-93.1791
Citation
B. L. Lin, "Field Monitoring and Analysis of Envelope Pile in Shijiazhuang Six-Line Tunnel", Applied Mechanics and Materials, Vols. 90-93, pp. 1791-1794, 2011
Online since
September 2011
Authors
Export
Price
$32.00
Share

In order to see related information, you need to Login.

In order to see related information, you need to Login.

Authors: Shu Jie Zhang, Rui Wang, Chong Qi Ma
Chapter 5: Structure, Properties and Processes of Textile Materials
Abstract:The tubular textile composite material as the liner is inversed in the pipeline by gas or water pressure, and then the damaged pipeline can...
945
Authors: Lin Li
Chapter 6: Geotechnical Engineering and Underground Space Structure
Abstract:Shrinkage induced tensile force was observed in a 264m long reinforced concrete struts through field monitoring during a foundation...
2880
Authors: Hong Jian Lu
Chapter 2: Manufacturing Technology
Abstract:In order to study the force mechanism and reinforcement effect of high-pressure second grouting method in leading support of soft-fracture...
768
Authors: Si Si Liu, Xue Liang Jiang
Chapter 1: Geological and Geotechnical Engineering
Abstract:According to energy principle, numerical methods of axial force and displacement of tension-type anchor are derived. Firstly, mechanism of...
63
Authors: Li Jun Zhou, Ziai Lu, Wen Juan Wang
Chapter 1: Geological and Geotechnical Engineering
Abstract:Pile foundation design has gradually used the super-long pile structure form with the port and offshore engineering construction developing...
471