Influences of Loading Mode and Construction Speed on Position of Phreatic Line of a Tailings Dam
  Abstract

The location of phreatic line of a tailings dam is of significant importance on the stability of the tailings dam. In this study, extensive numerical analysis in ABAQUS have been performed to study the influences of loading mode and construction speed on position of the phreatic line of tailings dam in the process of construction from the existing elevation of 59 m to the final elevation of 100 m. The results show that the location of the phreatic line changes very little at the lower part of the dam; by contrast, the location of phreatic line dramatically changes at the upper part of the dam. At a certain construction speed, loading mode has negligible influence on the position of the phreatic line during the duration of one rising round for the tailings dam. The construction speed has more significant influences on the position of phreatic line in the middle term in the service duration of the tailings dam than in the later period.

  Info
Periodical
Advanced Materials Research (Volumes 261-263)
Edited by
Jingying Zhao
Pages
1724-1728
DOI
10.4028/www.scientific.net/AMR.261-263.1724
Citation
W. D. Lei, T. L. Fu, R. Chen, W. B. Luo, "Influences of Loading Mode and Construction Speed on Position of Phreatic Line of a Tailings Dam", Advanced Materials Research, Vols. 261-263, pp. 1724-1728, 2011
Online since
May 2011
Export
Price
$32.00
Share

In order to see related information, you need to Login.

In order to see related information, you need to Login.

Authors: Chang Chun Wu
Chapter 8: Hydraulic Engineering
Abstract:Through project examples, this paper set up a two-dimensional finite element seepage flow model with the help of the Auto-BANK software, to...
2699
Authors: Shu Qi Ma, Si Jing Cai, Miao Guo
Chapter 3: Geotechnical and Structural Engineering
Abstract:As a major hazard installation in mine the safe and effective running of a tailings dam is very important, therefore the stability analysis...
1406
Authors: Liang Song, Zhen Xing Yang, Hao Wang, Zi Hao Wang, Huan Qiang Zhang
Chapter 1: Geological and Geotechnical Engineering
Abstract:The tailing pond of Wushan copper mine is located in a valley among the mountains, with kinds of hidden troubles like the overflow of the...
207
Authors: Zhen Zhong Shen, Liang Zhong, Xian Dun Chai
Chapter 1: Structural Engineering and Materials, Civil Engineering
Abstract:The Rumei core wall rockfill dam hydropower station is in Lancang River in the Mangkang county of the Tibet autonomous region with maximum...