Optimizing of Flow Control Devices in a Single Strand Continuous Casting Tundish
  Abstract

Flow control devices (weir and dam) in a continuous casting tundish are very important to the flow field, which influences the temperature uniform and the inclusion floating. In this work, the weir and dam were firstly optimized through numerical simulation and water simulation synthetically by orthogonal optimization tests. And the optimal parameters showed that the distance from upper weir to inlet was 1000 mm, the distance of upper weir to tundish bottom was 150 mm, the distance from upper weir to dam was 600 mm, and the height of the dam was 320 mm. Then the effect of different arrangement holes on the dam was discussed through RTD curve and velocity field under the optimum flow control device. And it revealed that the hole influenced the flow pattern in that area obviously, a dam with two holes could get a better flow field.

  Info
Periodical
Advanced Materials Research (Volumes 284-286)
Chapter
Iron and Steel
Edited by
Xiaoming Sang, Pengcheng Wang, Liqun Ai, Yungang Li and Jinglong Bu
Pages
1209-1215
DOI
10.4028/www.scientific.net/AMR.284-286.1209
Citation
L. L. Zhang, D. F. Chen, Q. Liu, M. Zhang, X. Xie, D. H. Luo, "Optimizing of Flow Control Devices in a Single Strand Continuous Casting Tundish", Advanced Materials Research, Vols. 284-286, pp. 1209-1215, 2011
Online since
July 2011
Export
Price
$32.00
Share

In order to see related information, you need to Login.

In order to see related information, you need to Login.

Authors: Ming Qin Liu, Y.L. Liu
Abstract:The purpose of this paper is to present a 2D depth-averaged model under orthogonal curvilinear coordinates for simulating two-dimensional...
2993
Authors: Chang Chun Wu
Chapter 8: Hydraulic Engineering
Abstract:Through project examples, this paper set up a two-dimensional finite element seepage flow model with the help of the Auto-BANK software, to...
2699
Authors: Chao Chen, Guo Guang Cheng, Hai Bo Sun, Xin Chao Wang, Jia Quan Zhang
Chapter 2: Iron and Steel
Abstract:The optimization of the location and height of weir & dam with drain holes in a single-strand continuous casting tundish was carried out from...
293
Authors: Sheng Qiang, Xiang Rong Wang, Zhi Qiang Xie, Zhan Qiang Zheng
Chapter 6: Applied Mechanics
Abstract:Before and after pouring the concrete for a dam, how to predict and obtain the accurate temperature and stress of the various parts of the...
1600
Authors: Shu Qi Ma, Si Jing Cai, Miao Guo
Chapter 3: Geotechnical and Structural Engineering
Abstract:As a major hazard installation in mine the safe and effective running of a tailings dam is very important, therefore the stability analysis...
1406