Paper Title:
Performance Indicators for Sapele Thermal Power Station, Nigeria: 1997-2006
  Abstract

Performance indices as measured by percentage of shortfall of energy generated, load factor, utilization factor and capacity factor of Sapele thermal power station, Nigeria in the period 1997 to 2006 is presented. The thermal station uses both steam and gas turbines. The station consists of six units of steam turbine and four units of gas turbine with total installed capacity of 1020 MW. But it was established that less than 17 % of the installed capacity was available. The percentage shortfall of energy generated for the period under review ranged from 27.4 to 49.1 %. This was due to aging of the plant, improper operation and maintenance. The load factor was between 39.9 and 64 % as against international best practice of 80 %. The inability of Power Holding Company of Nigeria (PHCN) to do turn-around maintenance on the plant was advanced for the dismal value. Average plant availability of the plant for the studied period was less than 21% as against Industry best practice of over 95 %. The capacity factor was even more dismal. For the period under review, it ranged from as low as 5.49 % in 2006 to the highest value of 17.19 % in 1997. Low capacity factor indicates excessive plant failure. Measures to improve the performance indices of the plant have been suggested such as training of operation and maintenance (O & M) personnel regularly, improvement in O & M practices, proper spare parts inventory, organizing regular management meetings and improving general housekeeping of the plant.

  Info
Periodical
Chapter
Chapter 9: Systems Design and Analysis
Edited by
A.O. Akii Ibhadode
Pages
667-675
DOI
10.4028/www.scientific.net/AMR.367.667
Citation
O. Obodeh, F. O. Isaac, "Performance Indicators for Sapele Thermal Power Station, Nigeria: 1997-2006", Advanced Materials Research, Vol. 367, pp. 667-675, 2012
Online since
October 2011
Export
Price
$32.00
Share

In order to see related information, you need to Login.

In order to see related information, you need to Login.

Authors: A.O. Melodi
Abstract:In this paper the normal regimes of the Nigerian 330-132 kV power grid at 2003-2005 year levels were analyzed. The load flow studies were...
87
Authors: A.O. Melodi
Abstract:A study of the growth dynamics of the installed capacity of the Nigerian Power System from 1963 to date was done. Perspective available...
114
Authors: A.C. Igboanugo
Abstract:There are several reasons why public power supply policy in Nigeria needs to be reviewed. This paper points out the justification based on...
73
Authors: Yan Zhang, Xiao Long Tang, Hong Hong Yi, Qiong Fen Yu, Kai Li, Dan He, Jiang Hao Song
Abstract:The present status of iron and steel industry of China and Yunnan were given in this work. Base on the analysis of iron and steel industry of...
895
Authors: Yan Wang, Guang Fu Liu, Shou Xu Song, Ping He
Abstract:This paper deals with the energy-saving product design involving the product energy property into design process. On the basis of the energy...
1443