An Alternative Method of Estimating Piping Construction Projects

Article Preview

Abstract:

This research involves developing a project management system for the piping construction projects. Piping construction as a part of mechanical package usually takes over 30% of total efforts for the industrial construction projects, thus is typically recognized as a critical work scope for the similar kinds of construction projects. Therefore, the piping construction under budget and within schedule is one of the crucial tasks for management, and it takes accurate prediction of performance throughout the project execution process. The researchers suggest an alternative model be utilized to accurately forecast piping work efforts required for the piping construction. The model developed incorporates difficulty factors to estimate the level of efforts more accurately and the validation of the model is in progress. The alternative method of forecast may improve the accuracy significantly.

You might also be interested in these eBooks

Info:

Periodical:

Pages:

1131-1136

Citation:

Online since:

May 2012

Export:

Price:

Permissions CCC:

Permissions PLS:

Сopyright:

© 2012 Trans Tech Publications Ltd. All Rights Reserved

Share:

Citation:

[1] S.W. Son , J.S. Yoon, J.H. Paek, A Study on Construction Productivity Measurement Method, Journal of Architectural Institute of Korea, Vol.19 No.10, (2003), P.101~108

Google Scholar

[2] J.H. Park, D.Y Kim, H.K Lee, The Study on Correlation Between Factors Decreasing Construction Productivity and Waste Factors with Relation to Lean Construction, Korean journal of construction engineering and management, Vol.4 No.4, (2003), P.164~172

Google Scholar

[3] Y.S. Cho, H.S. Cha, A Study of Project Characteristics and Project Performance Level of Difficulty, Korean journal of construction engineering and management, Vol.11 No.6, (2010), P.78~88

DOI: 10.6106/kjcem.2010.11.6.78

Google Scholar

[4] Y.S. Ahn, K.R. Song, J.M. Heo, Improving the Accuracy of Screening of Cost Estimation in Early Construction Project Phase, Journal of Architectural Institute of Korea, Vol.19 No.11, (2003), P.133~140

Google Scholar

[5] S.H. An, J.E. Yoon, K.G. Kang, A Study on the Assessment Model of Preliminary Cost Estimates Using Discriminant Analysis, Journal of Architectural Institute of Korea, Vol.21 No.09, (2005), P.169~176

Google Scholar

[6] S.H. An, U.Y Park , A Study on the Key Factors Influencing the Reliability of Conceptual cost estimates in Building Construction Projects, Journal of Korea Institute of Building Construction, Vol.8 No.4, (2008), P.53~59

DOI: 10.5345/jkic.2008.8.4.053

Google Scholar

[7] S.W. Moon, S.C. Park, K.N. Kwon, Approximate Estimating of Plant Construction Duration Using a Standard Schedule Model, Korean journal of construction engineering and management, Vol.10 No.2, (2009), P.26~33

Google Scholar

[8] 2010 Mechanical Equipment Standaed Cost Data, Edited by Construction Research Publishing in (2010)

Google Scholar