Rapid Excavation Research of Half Coal Rock Lane in Liu-Wan Mine

Article Preview

Abstract:

In order to solve the question of excess or under excavation, poorly forming around the lane, low rate of excavation caused by less drilling, arbitrarily drilling, non-standard charging, unreasonable initiation network in the construction process of half coal rock lane in Liu-wan mine. According to coal and rock conditions at the scene and through theoretical calculations and engineering analogy, made a scientific and rational borehole layout and correct initiation network, strengthened temporary support and changed operation modes. The driving rate of the single circulation was improved from 1.6m to max.2.75m. The utilization rate of the blasting boreholes was improved from 89% to previous 94.7%. The unit consumption of explosives was significantly reduced from the original 1.24kg/m3 minimum to 0.74 kg/m3.Thus the profile shape results would be good and the driving speed could be highly increased. Research results will be the same geological conditions for excavating to provide reference.

You might also be interested in these eBooks

Info:

Periodical:

Pages:

418-423

Citation:

Online since:

May 2012

Export:

Price:

Permissions CCC:

Permissions PLS:

Сopyright:

© 2012 Trans Tech Publications Ltd. All Rights Reserved

Share:

Citation:

[1] Xingdong Zhao, Liangwu Shi. Alley of Engineering [M]. Xuzhou: China mining university publishes, 2004. ( in Chinese)

Google Scholar

[2] Hongsong Wei. Alley of Engineering [M]. Beijing: Coal industry publishes, 2007. ( in Chinese)

Google Scholar

[3] Dongming Guo, Renshu Yang, Kunlun Hu etc. Experimental Research on Long Hole Loose Blasting Mechanized Kaolin Mining [J]. Mining and Safety Engineering Journal, 2009, 26(4):428-432. ( in Chinese)

Google Scholar

[4] Qing Li. Experiment of Fracture Behaviors and Control for Crack Propagation under Blasting Load [D],China University of Mining and Technology(Beijing), Beijing:2009. ( in Chinese)

Google Scholar

[5] Kunlun Hu, Renshu Yang, Xiaofeng Xu, Xinmin Ma. Blasting Test and Study on Driving of Deep-Seated Rock Tunnels of Coal Mines [J]. China Journal of Liaoning Technical University, 2007, 26(6):856-858. ( in Chinese)

Google Scholar

[6] Qing Li, Renshu Yang, Zenglu Tang, Research on rapid excavation technology for deep mine large cross sectional rock roadway [J]. Coal Science and Technology, 2006, 34(10):1-4. ( in Chinese)

Google Scholar

[7] Erxin Gao, Renshu Yang. Blasting Engineering [M]. Xuzhou: University of Mining and Technology (Beijing), 1999. ( in Chinese)

Google Scholar

[8] Renshu Yang, Zhiqiang Zhang, Qiang Sun. Research on Drilling and Blasting Yechnology for Deep Mine Hard Rock Roadway in Huainan Mining Area [J]. Coal Science and Technology, 2005, 33(2):42-45. ( in Chinese)

Google Scholar

[9] Changwei Xin. Half Coal Crag Lane Formation Engineering Research and Discusses [J]. Shandong Coal Technology, 2008(6): 113-114. ( in Chinese)

Google Scholar

[10] Chen Shicheng. Improve half coal rock heading of several ways of fast speed [J]. Inner Mongolia coal economic, 2003(5): 54-55. ( in Chinese)

Google Scholar

[11] Dong Xucheng. Reasonable roof supporting method is to accelerate the ensemble dug coal rock face of half the progress key [J]. Heilongjiang science and technology information, 2011(9): 65-66. ( in Chinese)

Google Scholar