Procedure Inversion Effect Analysis of Final System Transformation of Prestressed Concrete Continuous Girder Bridge

Article Preview

Abstract:

When the cantilever construction is adopted by the prestressed concrete continuous girder bridge, the order of two key procedures between removing temporary support and tensing remanent prestressed cable is used to be ignored. In order to study the influence of procedure inversion, the influences on bridge shape, stress distribution and prestressing loss were calculated for one common prestressed continuous concrete box girder bridge by MIDAS CIVIL 2006, respectively. The obtained result presents that: the influence on the bridge shape and the prestressing loss are not apparent, but the influence on the stress distribution is serious; the maximal compressive stress of procedure inversion is more 42.3% than common construction procedure only by tensing the remaining steel beams at box girder; especially, the combining area between the box girder and temporary support is easy to pull out. So, the procedure inversion construction method cant be accepted.

You might also be interested in these eBooks

Info:

Periodical:

Pages:

1323-1327

Citation:

Online since:

January 2014

Authors:

Export:

Price:

Permissions CCC:

Permissions PLS:

Сopyright:

© 2014 Trans Tech Publications Ltd. All Rights Reserved

Share:

Citation:

* - Corresponding Author

[1] Ma Baolin. High pier and long-span continuous rigid frame bridge. Beijing: people's communications press, (2001).

Google Scholar

[2] Lei Junqing. The design and construction of bridges. Beijing: people's communications press, (2000).

Google Scholar

[3] Zhang Jiyao, et al. Cantilever casting Prestressed concrete continuous girder bridge. Beijing: people's communications press, (2000).

Google Scholar

[4] He Xuhui, Qiu Boyong. Investigation of the related issues of the prestressed concrete continuous beam cantilever construction [J]. railway construction technology, 2000, (1): 13-17.

Google Scholar

[5] Liu Liming, Ning Pinghua, Xiong Zhengyuan, et al. The construction control of prestressed concrete continuous beam with 138 m main-span [J]. City Bridges & flood control, 2002, (1): 53-58.

Google Scholar