This essay introduces a construction case of demolishing the scrapped concrete overpass over the existing railway using the mobile protective scaffolding during the construction of an overpass reform project. When the overpass demolishing project is staging into the phase of right over the railway, moving the mobile protective scaffolding to the appropriate position guarantees an easy way for the demolishing of the scrapped overpass above as well as a safe journey for the railway. After the demolishing project, the scaffolding can be removed and dismantled. The stability of the mobile protective scaffolding structure and the design of the member response is discussed in this essay, meanwhile the controlling key points of the scaffolding during the construction is also sketched.

You might also be interested in these eBooks

Info:

Periodical:

Pages:

784-789

Citation:

Online since:

July 2014

Export:

Price:

Permissions CCC:

Permissions PLS:

Сopyright:

© 2014 Trans Tech Publications Ltd. All Rights Reserved

Share:

Citation:

[1] Zhang jian-min, Chen Bao-Liang, Li Da. High-speed railway shacks stents aerodynamic effect analysis [J]. Railway standard design, 2010 (2): 91-93.

Google Scholar

[2] Southwest Jiao tong university. The aerodynamic effect of high-speed train by shacks scaffolds calculation analysis [R]. Chengdu: southwest Jiao tong university, (2009).

Google Scholar

[3] TB10002. 1-2005, [S] Railway Bridge and culvert design basic specifications. Beijing: China railway publishing house, (2005).

Google Scholar

[4] GB50017-2003, steel structure design specification [S]. Beijing: China planning press, (2003).

Google Scholar

[5] GB50009-2001, [S] load code for the design of building structures. Beijing: China building industry press, (2001).

Google Scholar

[6] Shanghai railway bureau. Safe construction on knowledge [G]. (2009).

Google Scholar

[7] The army and Ma Bin. Movable scaffolding across existing lines in construction of protective application [J]. Railway standard design, 2011 (6): 111-113.