Connecting Passage Construction for the Foundation Pit under Existing Optical Fiber Cable
Abstract:
Puli center project protects the original soil with pipe roof technology through combining the field analysis and finite element modeling while constructing the connecting passage of foundation pit under the existing optical fiber cable, so as to avoid the optical fiber cable from producing too big settlement to cause the adverse effect, and then constructs the connecting passage of foundation pit. After field monitoring, the maximum settlement of pipeline conforms to the deformation control standard of optical fiber cable, and this technology has certain innovation, which can provide reference for the similar project.