Asymmetric Construction Technology of Partially Cable-Stayed Bridge with Single Tower and Single Cable Plane
Abstract:
According to the structural characteristics and the surrounding environment of partially cable-stayed bridge, an asymmetric construction method combinded with support cast-in-place and cantilever casting is applied for main girder construction, based on project of Yuyao cable-stayed bridge. Its basic idea is as follows: One deck section is concreted with brackets in advance, which to offer counterweight for basket construction symmetrically. The technical features and construction key point are described in detail, which provides reference for similar bridge construction.