Research on Construction Schedule Real-Time Control of High Core Rock-Fill Dam Based on Digital Monitoring

Article Preview

Abstract:

The real-time control of the construction schedule for the high core rock-fill dam is researched, and the construction schedule forecasting and analysis method for the high core rock-fill dam is proposed based on the real-time monitoring and simulation. According to the basic principles of schedule control, the control process of construction schedule for the high core rock-fill dam is established, and the implementation method of the dynamic adjustment and control for construction schedule of the high core rock-fill dam is put forward by comparing the current construction schedule with the plan and combining measures such as earthwork dynamic balance optimization and dynamic adjustment and optimization of construction method. The achievement has been used in a hydropower project in southwest China, which provides strong technical support for the high standard construction of the project.

You might also be interested in these eBooks

Info:

Periodical:

Advanced Materials Research (Volumes 588-589)

Pages:

1062-1067

Citation:

Online since:

November 2012

Export:

Price:

Permissions CCC:

Permissions PLS:

Сopyright:

© 2012 Trans Tech Publications Ltd. All Rights Reserved

Share:

Citation:

[1] Pillai A S, Tiwari A K, Enhanced PERT for programme analysis, control and evaluation: PACE. Int. J. Proj. Manage, 1995, 13(1): 39~43.

DOI: 10.1016/0263-7863(95)95702-f

Google Scholar

[2] Kim K, Jesús M. de la Garza, Critical Path Method with Multiple Calenders, J Constr Eng Manage, ASCE, 2005, 131(3): 330~342.

DOI: 10.1061/(asce)0733-9364(2005)131:3(330)

Google Scholar

[3] Lee H S, Ryu H G, Yu J H, et al, Method for Calculating Schedule Delay Considering Lost Productivitis, J Constr Eng Manage, ASCE, 2005, 131(11): 1147~1154.

DOI: 10.1061/(asce)0733-9364(2005)131:11(1147)

Google Scholar

[4] Wilde E, Engineering project control, Proj. Manage., 1995, 12: 279~283.

Google Scholar

[5] Hu C S, Optimization of construction schedule and control method in hydroelectric project (in Chinese). Tianjin, TJU, (2005).

Google Scholar

[6] Cui B, Hu L X, Liu D H. Development and application of the real-time monitoring system for filling construction process of high core rock-fill dam. Engineering Sciences (in Chinese), 2011, 13(12): 91-96.

Google Scholar

[7] Zhong D H, Zhang P, Theory and application of construction simulation for high core rock-fill dam based on real-time monitoring, Water Resources and Hydropower Engineering (in Chinese), 2009, 40(8): 103~107.

Google Scholar

[8] Zhong D H, Zhang P, Wu K X, Theory and practice of construction simulation for high rock-fill dam, Sci China Ser E Technol Sci, 2007, 50(1): 51~61.

DOI: 10.1007/s11431-007-6006-6

Google Scholar