Experimental Study on Fire Resistance Properties of Post-Installed Rebar Connection

Article Preview

Abstract:

A serial of fire tests have been conducted to study the fire resistance of the post-installed rebar connection with organic adhesive. Research variables include three kinds of anchorage depth. Loads are applied to specimens through lever and remain a constant throughout the whole process of the tests. The temperatures of connections are elevated following the ISO834 curve and the failure is controlled by excessive deflection of bonded-in rebar beams. The test results show that anchorage depth has a great influence on the performance of bonded-in rebar beams exposed to fire. Beams using organic adhesive fail suddenly with obvious rebar slip, and behave with poor fire endurance.

You might also be interested in these eBooks

Info:

Periodical:

Advanced Materials Research (Volumes 671-674)

Pages:

1877-1882

Citation:

Online since:

March 2013

Export:

Price:

Permissions CCC:

Permissions PLS:

Сopyright:

© 2013 Trans Tech Publications Ltd. All Rights Reserved

Share:

Citation:

[1] Xingang Zhou. 2003. Anchorage Behavior of Post-embedded Bars in Concrete Subjected to Tension,. Chinese Journal of Rock Mechanics and Engineering, 22/7 , 1169-1173(in Chinese).

Google Scholar

[2] Chengzhi Xiao, Wenling Tian and Wenjun Sun. 2010. Experimental research on parameters affecting anchorage performance of post-installed bars in concrete,. Journal of Building Structures S2: 275-278(in Chinese).

Google Scholar

[3] Changqing Liu, Zhoudao Lu and Zhanhong Li. 2010. Experimental Study on the Pullout Strength of Bonded Rebar Under Fire (High Temperature) ,. Journal of Sichuan University (Engineering Science Edition) Vol. 42, No. 1: 75-79 (in Chinese).

Google Scholar

[4] Changqing Liu,Zhoudao Lu and Xiuqiu Zhang. 2010. Experimental study on ultimate strength of post-installed rebar subjected to fire,. Journal of Harbin Institute of Technology Vol. 42, No. 12: 1958-1961(in Chinese).

Google Scholar

[5] Changqin Liu, Kongfan Wang and Zhoudao Lu. 2011. Design Method of Single Post-Installed Rebar Exposed to High Temperature,. Structural Engineers, Vol. 27, No. 5: 85-89(in Chinese).

Google Scholar

[6] Yong Zou, Zhoudao Lu and Jiangtao Yu. 2011. Experimental Study on Ultimate Strength of Post-Installed Rebar Connection Members in Fire,. Structural Engineers, Vol. 27, No. 3: 92-97(in Chinese).

Google Scholar

[7] Guanglin Yuan, Tao Liu and Yuhong Yan. 2008. Experimental Study of Behaviors of RC Structure's Exterior Joints with Post-Embedded Bars Under Cyclic Loading After Treatment at High T emperature,. Journal of China University of Mining & Technology, Vol. 37, No. 1: 19-23(in Chinese).

Google Scholar

[8] Zhenhai Guo and Xudong Shi, in: Experiment and Calculation of Reinforced Concrete at Elevated Temperatures, Tsinghua University Press(2003).

Google Scholar

[9] GB 50367-2006 Degin code for strengthening concrete structure.2006. China Architecture and Building Press.

Google Scholar

[10] JGJ 145-2004 Technical specification post-installed fastenings in concrete structures. 2005. China Architecture and Building Press.

Google Scholar