Research on Algorithms of Critical Path Searching and Time Optimization in Construction Projects

Article Preview

Abstract:

Because other consequential damages brought about by the construction delay can not be estimated, so the guarantee period or even ahead of schedule becomes particularly important. The critical path usually determines the progress of the construction. However, because of its own deficiencies, the traditional critical path algorithm cannot accurately describe the overlap between activity and interaction. So, in the paper, matrix method for critical path (CPMM) is designed for CP, and its rules and calculating process are described in detail. Through experiments, the effectiveness of CPMM is proved.

You might also be interested in these eBooks

Info:

Periodical:

Advanced Materials Research (Volumes 838-841)

Pages:

3233-3236

Citation:

Online since:

November 2013

Export:

Price:

Permissions CCC:

Permissions PLS:

Сopyright:

© 2014 Trans Tech Publications Ltd. All Rights Reserved

Share:

Citation:

* - Corresponding Author

[1] Yang Feixue, Hong Chuanjun. Research on ProjectDelay C laim Event in Concurrent Delay Science Technology and Engineering, Vol. 8 (2008), p.119.

Google Scholar

[2] Yin Renkun: Data Structure (Tsinghua University Press Publications, Beijing china 2012).

Google Scholar

[3] Ma Junjie, Qi Jianxun. Study on Critical Path Method with Fixed Time Parameter in Network Planning Technology, Information Science and Engineering (ISISE), 2010 International Symposium on Digital Object Identifier: (2010), p.166.

DOI: 10.1109/isise.2010.96

Google Scholar

[4] Information on http: /www. chinatat. com/new/201108/yi6762131334192811025369. shtml.

Google Scholar