A Model for Comparative Analysis of Inventory Costs of JIT and EOQ Purchasing in the Ready Mixed Concrete Industry

Article Preview

Abstract:

A model for comparing the inventory costs of purchasing under the economic order quantity (EOQ) system and the just-in-time (JIT) order purchasing system in existing literature concluded that JIT purchasing was virtually always the preferable inventory ordering system especially at high level of annual demand. By expanding the classical EOQ model, this paper shows that it is possible for the EOQ system to be more cost effective than the JIT system once the inventory demand approaches the EOQ-JIT cost indifference point. The case study conducted in the ready-mixed concrete industry in Singapore supported this proposition.

You might also be interested in these eBooks

Info:

Periodical:

Materials Science Forum (Volumes 532-533)

Pages:

1020-1023

Citation:

Online since:

December 2006

Authors:

Export:

Price:

Permissions CCC:

Permissions PLS:

Сopyright:

© 2006 Trans Tech Publications Ltd. All Rights Reserved

Share:

Citation:

[1] F. Chyr, T.M. Lin and C.F. Ho: Engineering Costs and Production Economics, Vol. 18 (1990) No. 3, pp.233-240.

Google Scholar

[2] M.J. Schniederjans and Q. Cao: International Journal of Production Economics, Vol. 65 (2000) No. 3, pp.289-294.

Google Scholar

[3] M.J. Schniederjans and Q. Cao: International Journal of Physical Distribution & Logistics Management, Vol. 31 (2001) No. 2, pp.109-123.

Google Scholar

[4] M. Wu: Modeling JIT Purchasing in the Ready Mixed Concrete Industry (Unpublished PhD thesis, the National University of Singapore 2004).

Google Scholar

[5] F.W. Harris: Operations and Cost - Factory Management Series (A.W. Shaw Co, Chicago 1915).

Google Scholar

[6] N. Gaither: Production and Operations Management (Duxbury Press, Belmont, CA 1996).

Google Scholar

[7] K.A. Wantuck: Just-In-Time for America: A Common Sense Production Strategy (The Forum Ltd., Milwaukee, WI 1989).

Google Scholar

[8] I.D. Tommelein and A.E. Y Li: Proceedings of the 7 th Annual Conference of the International Group for Lean Construction, Berkeley, Calif., pp.97-108.

Google Scholar