A New Buffer Setting Method Based on Activity Attributes in Construction Engineering

Article Preview

Abstract:

The direct application of the Theory of Constraints (TOC) to construction engineering, known as Critical Chain Management and Buffer Management (CCM/BM), has recently emerged as one of the most popular approaches to schedule management. However, the existing buffer setting techniques have less aken the activity attributes into account. In this paper, we introduce the concept of structure entropy to reflect the complexity of schedule network of construction project and propose a novel method for buffer sizing based on an in-depth analysis of activity attributes. After simulation test and comparison with classical methods, the proposed method is proved to have better accuracy and effectiveness.

You might also be interested in these eBooks

Info:

Periodical:

Pages:

3274-3281

Citation:

Online since:

May 2012

Export:

Price:

Permissions CCC:

Permissions PLS:

Сopyright:

© 2012 Trans Tech Publications Ltd. All Rights Reserved

Share:

Citation:

[1] K. Rezaie, B. Manouchehrabadi, and S.N. Shirkouhi: Duration estimation, a new approach in Critical chain scheduling. Third Asia International Conference on Modelling & Simulation, Vol. 1&2, pp.481-484, 2009.

DOI: 10.1109/ams.2009.67

Google Scholar

[2] E.M. Goldratt: Critical Chain. (The North River Press Publishing Corporation.USA. 1997)

Google Scholar

[3] Jagathipriya, R.P. Byali, and M.V. Kannan: Journal of Spacecraft Technology. Vol. 18(1) (2008), pp.30-36.

Google Scholar

[4] O.I. Tukel, W.O. Rom, and S.D. Eksioglu: European Journal of Operational Research. Vol. 172(2) (2006), pp.401-416.

Google Scholar

[5] L.D. Long, and A. Ohsato: International Journal of Project Management. Vol. 26(6) (2008), pp.688-698.

Google Scholar

[6] R.C. Newbold: Project Management in the Fast Lane: Applying the Theory of Constraints. (St.Lucie Press. USA. 1998)

Google Scholar

[7] L.P. Leach: Critical Chain Project Management. (Artech House. USA. 2000)

Google Scholar

[8] W. Herroelen, R. Leus, and E. Demeulemeester: Project Management Journal. Vol. 33(4) (2002), pp.46-60.

Google Scholar

[9] W. Herroelen, and R. Leus, and E. Demeulemeester: Journal of Operations Management. Vol. 19(5) (2001), pp.559-577.

Google Scholar

[10] M. Rabbani, S. Ghomi, F. Jolai, and N.S. Lahiji: European Journal of Operational Research. Vol. 176(2) (2007), pp.794-808.

DOI: 10.1016/j.ejor.2005.09.018

Google Scholar

[11] P. Gao, and J. Feng: Industrial Engineering and Management. Vol. 14(3) (2009), pp.55-9.

Google Scholar

[12] Z.Y. Zhao, W.Y. You, and Q.L. Lv: "Applications of Fuzzy Critical Chain Method in Project Scheduling." in ICNC 2008: Fourth International Conference on Natural Computation, Vol. 6, pp.473-477, 2008.

DOI: 10.1109/icnc.2008.29

Google Scholar

[13] G. Battail: BIOSEMIOTICS. Vol. 2(3) (2009), pp.303-320.

Google Scholar