First Drainage Vent Test of Diversion Tunnel of DJIPLOHO Hydropower Station
Abstract:
DJIPLOHO conducts the first drainage vent test of diversion tunnel after completing in the construction of hydropower station with a water commissioning. Through the data analysis and research for the testing process, it is necessary and has flexibility to adjust accurately the drainage. Test results verify the rational design and safety of the tunnel and prove the correctness of first drainage tests procedures. It also accumulates valuable experience for the same type of drainage project for the first time.
Info:
Periodical:
Pages:
556-560
Citation:
Online since:
October 2013
Authors:
Keywords:
Price:
Сopyright:
© 2013 Trans Tech Publications Ltd. All Rights Reserved