Study on Numerical Simulation of Construction Processing for No.1 Shaft of Weihe Tunnel

Article Preview

Abstract:

In order to analyze the construction processing for No.1 shaft of Weihe Tunnel on Baoji-Lanzhou Passenger-dedicated Railway, a two-dimensional numerical model for the simulation of the shaft was built with the finite difference method. Mohr-Coulomb model was chosen as the soil constitutive model. The result shows that the maximum lateral displacement appears at the upper part of the shaft, and the lateral displacement is in effective constraint at the shaft’s bottom. After the construction, the maximum uplift at the shaft’s bottom is in the center, while the uplift decreases from the shaft’s center to its both sides. The maximum pressure stress turns up at the bottom sides of the shaft, and the maximum tensile stress appears at the middle of the shaft.

You might also be interested in these eBooks

Info:

Periodical:

Pages:

837-841

Citation:

Online since:

September 2014

Export:

Price:

Permissions CCC:

Permissions PLS:

Сopyright:

© 2014 Trans Tech Publications Ltd. All Rights Reserved

Share:

Citation:

* - Corresponding Author

[1] Rong Zhou. Study on Numerical Simulation on Construction Processing for a Silo of the DaPingLi Tunnel[D]. Wuhan: Huazhong University of Science and Technology, 2007. (in Chinese).

Google Scholar

[2] Yuebao Deng. Analytical Theory and Finite Element Analysis for Consolidation of Soft Soils by Vertical Drains[D]. Hangzhou: Zhejiang University, 2013. (in Chinese).

Google Scholar

[3] Highway Tunnel Design Specification (JTG D70-2004). Ministry of Communications of the People's Republic of China.

Google Scholar

[4] Tianlong Li. Monitoring and Simulation Analysis and Research on Excavation of Foundation Pit[D]. Hefei: Hefei University of Technology, 2012. (in Chinese).

Google Scholar