Scaffolding Erection Program of a Certain Project
Abstract:
This project is the construction and demolition program of the double-pole scaffolding for the exterior decoration of Building No.1 and No.2 of Wanda Plaza in an inland city. The exterior walls of ground floor stores are mainly comprised of granite columns, lacquer finishes, GRC plates, 8+8 toughened laminated glass canopy and other decorative items, with the highest elevation of 17.4m. Since other construction units need to dig electricity trenches and bury cables at a distance of 1.7m to the wall, the erection of the scaffolding should be limited to 1.5m from the wall.