Numerical Simulation Study on Technology of the Top-Down Bored Excavation with Cast-In Situ Arch

Article Preview

Abstract:

The top-down bored excavation with cast-in-situ arch method has many advantages, such as forming a complete and stable mechanical structure, reducing construction procedures and the frequency of structure transformation, improving the stability of structure during the construction and so on. According to the specific project of single span top-down bored excavation duct in Changchun Liberation Road station, numerical simulation method is used and finite difference software FLAC 3D is adopted in this paper to analyze and research the applicability of the top-down bored excavation with cast-in-situ arch method to this project. Then optimization analysis for excavation sequence of pilot tunnel is done and the optimum construction scheme is raised to guide the practical project. This research has certain practical significance and also provides references for similar projects.

You might also be interested in these eBooks

Info:

Periodical:

Pages:

1027-1032

Citation:

Online since:

March 2015

Authors:

Export:

Price:

Permissions CCC:

Permissions PLS:

Сopyright:

© 2015 Trans Tech Publications Ltd. All Rights Reserved

Share:

Citation:

* - Corresponding Author

[1] Meiqun Huang. Urban Rapid Rail Transit, 2009,22(6):66-70.

Google Scholar

[2] Mei Zhang. Study on Design and Technology for Building Subway Station with Tunneling and TOP 一 down Method [D]. SouthwestJiaotongUniversity. (2002).

Google Scholar

[3] Mengshu Wang. The General Theory of Underground Mined in Shallow Stratum in Chinese [M]. Anhui Education Publishing House, (2005).

Google Scholar

[4] Meiqun Huang. Urban Rapid Rail Transit, 2012,25(5): 84-87.

Google Scholar

[5] Wenbin Peng. FLAC 3D Practical Guide [M]. Beijing: Machinery Industry Publishing House,(2007).

Google Scholar

[6] Jianjun Luo, Dingli Zhang, Mengshu Wang, Chengping Zhang. Railway Construction Technology, 2006(5):1-4.

Google Scholar