Abstract:

In the construction process of Hong Kong-Zhuhai-Macao Bridge, the side span girder of Qingzhou channel bridge, the non-navigable span of the shallow water region and the side span S11 ~ S17 large segments are located between transitional pier and auxiliary pier of Jiuzhou channel bridge are based on the large segment hoisting construction technique. The widely use of the large segment hoisting construction which can ensure the construction safety and shorten the construction period obviously, effectively reduce the bad environment factors in construction. All of these are important to the transportation hub, Hong Kong-Zhuhai-Macao Bridge. But because of the transformation of structural system and the complex stress of the large segment girder in the lifting point in transportation and hoisting process, it is significant to do the finite element simulation analysis.

You might also be interested in these eBooks

Info:

Periodical:

Advanced Materials Research (Volumes 919-921)

Pages:

551-555

Citation:

Online since:

April 2014

Export:

Price:

Permissions CCC:

Permissions PLS:

Сopyright:

© 2014 Trans Tech Publications Ltd. All Rights Reserved

Share:

Citation:

* - Corresponding Author

[1] Liu Minghu, Meng Fanchao, Li Guoliang. Hong kong-zhuhai-macao bridge qingzhou Channel Bridge engineering characteristics and key technology [J] Bridge Construction, 2013, 43(4) 87 to 93.

Google Scholar

[2] Zhang Yongtao, Zhou Renzhong, Gao Jibing. Chung kai bridge coarse period of integral lifting technology research. Wuhan [J] The Chinese and Foreign Road. 2010 (6), 132 to136.

Google Scholar