The Review of Project Management Based on the Theory of Constraints and Critical Chain

Article Preview

Abstract:

Abstract. The relationship between precedence and successor activities is the only factor that determined the project scheduling in the traditional project scheduling management. The critical chain-an elegant solution, on the other hand, takes resource limitations into account and is composed of sections that are dependent on successor relationships and other sections that are dependent on resource constraint. By integrating the existing research findings, it is the objective of this paper to highlight the merits and pitfalls of the CCPM scheduling method, such as the principle for project delays, the critical chain identification; the time buffer setting and project scheduling with limited capacity of a resource. Furthermore, it also presidents the difficulties when implementing the critical chain approach and conclude with a description of our ongoing research direction.

You might also be interested in these eBooks

Info:

Periodical:

Pages:

3424-3430

Citation:

Online since:

May 2012

Export:

Price:

Permissions CCC:

Permissions PLS:

Сopyright:

© 2012 Trans Tech Publications Ltd. All Rights Reserved

Share:

Citation:

[1] Goldratt E M: M. Cox J: M. Aldershot. England: Gower, (1993)

Google Scholar

[2] Goldratt E M: M. Aldershot. England: Gower, (1994)

Google Scholar

[3] Goldratt E M: M. NY: The North River Press, (1990)

Google Scholar

[4] Goldratt E M: M. NY: North River Press, (1997)

Google Scholar

[5] Kevin J. Watson, John H. Blackstone, Stanley C. Gardiner. J. Journal of Operations Management, Vol. 25, No.2 (2007), p.387–402

Google Scholar

[6] Herman Steyn: J. International Journal of Project Management, Vol.19, No. 6(2000), P.363-369

Google Scholar

[7] Margaret F. Shipley, Andre de Korvin, Khursheed Omer: J. Eng. Technol. Manage, Vol. 14 (1997), P.49-65

Google Scholar

[8] G. F. Ma, Q. Chen: J. Shang Hai Science of Management, Vol. 4(2006), P.70-74

Google Scholar

[9] Graham K. Rand. Critical chain: J. International Journal of Project Management, Vol. 18, No.3 (2000), P.173-177

Google Scholar

[10] X.Y. Bao, Y. L. Zhao: J. Journal of Lanzhou Jiaotong University, Vol. 28, No.1 (2009), pp.34-36

Google Scholar

[11] D. Z. Zhao, H. Liao and Y. L. Liu: J. Journal of Tianjin University of Technology, Vol. 21, No.2 (2005), P.8-12

Google Scholar

[12] S. X. Liu, J. H. Song, and J.F. Tang: J. Control and Decision, Vol. 18, No.5 (2003), P.513-516

Google Scholar

[13] M. Bevilacqua, F. E. Ciarapica, G. Giacchetta: J. International Journal of Project Management, Vol. 27, No.4 (2009), P. 419–432

Google Scholar

[14] D. Z. Zhao and H. Liao: J. Industrial Engineering Journal, Vol. 8, No.2 (2005), P.4-6

Google Scholar

[15] Z. Li, Y. B. Ou and Y. Feng: J. Water Resources and Hydropower Engineering, Vol. 36, No.11 (2005), P.70-73

Google Scholar

[16] G. Y. Pan: J. Information Technique, P.173-175

Google Scholar

[17] W. Wan and C. Cai: J. Chinese Journal of Management Science, Vol. 10 (2002), P.155-160

Google Scholar

[18] Z. M. Li: J. Project Management Technology, Vol. 1(2008), P.68-72

Google Scholar

[19] C. Q. Zhang: J. Value Engineering, Vol. 10 (2010), P.88-90

Google Scholar

[20] C. M. Ye and D. Pan: J. Shan Xi Architecture, Vol. 36, No.19 (2010), P.185-187

Google Scholar

[21] Y. B. Dai and X. l. Ren: J. Computer Applications and Software, Vol. 26, No.10 (2009), P.127-129

Google Scholar

[22] G. P. Jiang and Y. W. Chen: J. Computer Application, Vol. 25, No.1 (2005), P.56-57

Google Scholar

[23] Y. W. Zhan: J. Construction, Vol. 2, No.3 (2010), P.145-149

Google Scholar

[24] K. L. Pan and L. Y. Yin: J. Chinese Literature. Vol. 4 (1997), P. 509-510

Google Scholar

[25] W. M. Han and X. Q.Xu: J. Business Modernization, Vol. 453, No.12 (2005), P.19-20

Google Scholar

[26] H. Steyn: J. International Journal of Project Management, Vol. 20, No.1 (2002), P.75-80

Google Scholar

[27] X. S. Yang and H. Hu: J. Industrial Engineering and Management, Vol. 2 (2005), P.48-52

Google Scholar

[28] N. Li and Z. M. Wu: J. Highway, Vol. 10 (2002), P.83-86

Google Scholar

[29] X. C. Li and G. M. Liu: J. Manufacturing information engineering of China, Vol. 40, No.7 (2001), P.1-4

Google Scholar

[30] Z. Shang:J. Chinese Space Science and Technology, Vol. 3, (2011), P .35-42

Google Scholar

[31] M. Zhang, Q. R. Chen and W. Q. Tang: J. Project Management Technology, Vol. 8, No.7 (2010), P.13-17

Google Scholar

[32] S. E. E. Elmaghraby, W. S. Herroelen and R. Leus: J. International Journal of Project Management, Vol. 21, No.4 (2003), P.301–305

Google Scholar

[33] W. Wan, C. Cai and C. F. Wang: J. Chinese Journal of Management Science, Vol.11, No.2 (2003), P.70-75

Google Scholar

[34] W. Wan and C. Cai:J. Chinese Journal of Management Science, Vol.11, No.1 (2003), P.4-8

Google Scholar

[35] X. Q. Wang, L. Y. Guo and T. Fu: J. Journal of Hebei University of Technology, Vol. 34, No.6 (2005), P.20-23

Google Scholar

[36] R. G. Luo, T. He and B. Wu: J. Journal of Wuhan University of Technology, Vol.29, No.11 (2007), P.129-132

Google Scholar

[37] S. X. Liu, J. H. Song and J. F. Tang:J. Act Automatic Sinica, Vol. 32 No.1 (2006), P.60-66

Google Scholar

[38] G. F. Ma, A. M. Wang and M.Z. Tu:J. Systems engineering Theory Methodology Applications, Vol. 13, No.2 (2004), P.167-171

Google Scholar

[39] G. F. Ma and L. Li:J.Project Management Technology, Vol. 9, No.2 (2011), P.23-26

Google Scholar

[40] W. D. Tian and N. F. Cui:J. Industrial Engineering and Management, Vol. 14, No.2 (2009), P. 88-93

Google Scholar

[41] J. J. Lin and G. H. Zhou:J. Science and Technology Management Research, Vol. 8 (2009), P.131-133

Google Scholar

[42] N. F. Cui and J. Liu: J. Industrial Engineering and Management, Vol. 14 No.3 (2009), P.60-64

Google Scholar

[43] W. M. Han, Q. Q. Gong and Z. Y. Liu: J. Journal of Jiangsu University of Science and Technology (Natural Science Edition), Vol. 23, No.1 (2009), P.75-78

Google Scholar

[44] M. Rabbani, S.M.T. Fatemi Ghomi, F. Jolai N.S. Lahiji: J. European Journal of Operational Research, Vol. 176, No.2 (2007), P.794–808

DOI: 10.1016/j.ejor.2005.09.018

Google Scholar

[45] B. Deng: J. Journal. Of HUST.(Urban Science Edition), Vol. 25, No.4 (2008), P.264-269

Google Scholar

[46] Y. Zhou and C. J. Feng: J. Science & Technology Progress and Policy, Vol. 25, No.2 (2008), P.174-176

Google Scholar

[47] Z. Y. Zhao, W. Y. You and Q. L. Lv: J. Journal of Railway Engineering Society, Vol. 5 (2009), P.98-102

Google Scholar

[48] Oya I. Tukel, Walter O. Rom and Sandra Duni Eksioglu: J. European Journal of Operational Research, Vol. 172, No.2 (2006), P.401–416

Google Scholar

[49] C. C. Zhu: J. System of Compute Production, Vol. 5(2008), P.1029-1035

Google Scholar

[50] Zinovy D. Radovilsky: J. Int. J. Production Economics, Vol. 55(2009), P.113-119

Google Scholar

[51] S. X. Liu, J. H. Song and J. f. Tang: J. Journal of System Engineering, Vol. 21, No.4 (2006), P.81-386

Google Scholar

[52] L. X. Yang, S. Q. Li, X. B. Huang and T. Peng: J. Industrial Engineering and Management, Vol. 1 (2009), P.11-14

Google Scholar

[53] Brucker P, Drexl A, Mohring R, et al: J. European j of Operational Research, Vol. 112, No.1 (1999), P.3-41

Google Scholar

[54] S. X. Liu, M. G. Wang and Y. Y. Nie: J. Journal of System Engineering, Vol. 16, No.1 (2001), P.55-60

Google Scholar

[55] M. Y. Shan, Y. Long. J. Project management Technology, Vol. 9 (2006), P.32-35.

Google Scholar