Research of Scheduling Management in Warship Scheduled Repair Project

Article Preview

Abstract:

The buffer setting and management mechanism in Critical chain method was combined with practical progress vanguard line in this paper. Then the information statistical and analysis methods of project schedule was given, and the methods are applied in project scheduling management of warship scheduled repair. With the application analysis in maintenance project shows that this methods can identify the activity chain which really lead to the lag of project scheduling. This shows that the method was given in this paper presents an applicable value for actual warship scheduled repair project scheduling management. CLC number: U672 Document id code: A

You might also be interested in these eBooks

Info:

Periodical:

Pages:

1564-1568

Citation:

Online since:

September 2013

Export:

Price:

Permissions CCC:

Permissions PLS:

Сopyright:

© 2013 Trans Tech Publications Ltd. All Rights Reserved

Share:

Citation:

* - Corresponding Author

[1] YiSheng Liu, in: Schedule Planning and Control for Engineering Project, edtied by YaoWu Wang Publications/China Architecture Industry Publishing, BeiJing (2008), in press. (in Chinese).

Google Scholar

[2] Bo Li, DongFeng Wen, Zhuobin Wei: Journal of Engineering Management: Vol. 26 No. 3(2012), p.71. (in Chinese).

Google Scholar

[3] XiaoMing Cui, Li Ma: Computer Engineering and Design: Vol. 31 No. 12(2010), p.2754. (in Chinese).

Google Scholar