Dynamic Scheduling Method for Steelmaking-Continuous Casting
Abstract:
A method of dynamic scheduling of steelmaking-continuous casting is proposed, which includes static scheduling based on genetic algorithm and dynamic scheduling based on scheduling rules, mathematical model and complete rescheduling utilizing genetic algorithm. The simulation with eight hours’ production data in S steel plant showed that the method could draw quickly a high quality and performable dynamic scheduling plan according to random production disturbance. The average utilization rate of converter could reach 95% and the generation period of initial scheduling is less than 3 minutes. The max dynamic scheduling adjustment period did not exceed 1 minute.