Analysis the Effect of Grouting Pressure on Shallow Soil Thickness which Covered the Shield Tunnel

Article Preview

Abstract:

Passing through the inland river the tunnel generally lead to overburden small thickness of overlying soil, the disturbance effect of shallow soil here is very large. So the research of the thickness of the overlying soil is the key to solve the engineering problems. The existing calculation formula of the thickness of covering soil only considering the static state after construction, does not take into account the grouting pressure to overlying soil disturbance during construction. Based on the existing thickness calculation formula, this paper attempts to get a new modified computational formula which take the grouting pressure into consideration, and puts forward the reasonable improvement according to different parameters.

You might also be interested in these eBooks

Info:

Periodical:

Advanced Materials Research (Volumes 1065-1069)

Pages:

353-357

Citation:

Online since:

December 2014

Export:

Price:

Permissions CCC:

Permissions PLS:

Сopyright:

© 2015 Trans Tech Publications Ltd. All Rights Reserved

Share:

Citation:

[1] DAI Xiao-ping, GUO Tao, QIN Jianshe: Research on minimum depth burial of shield tunnel machines crossing over ground base under rivers(Rock and Soil Mechanics, 2004, 27(5): 782-786).

Google Scholar

[2] ZHANG Qing-he, WANG Shen-tang, YAN Chang-zheng, et al. Tunneling methods through river(lake, sea)bed under shallow covering by shield(Chinese Journal of Rock Mechanics and Engineering, 2004, 23(5): 857-861).

Google Scholar

[3] XIAO Ming-qing, SUN Wen-hao, HAN Xiang-yang. Research on upward moving of segments of shieldtunel( Rock and Soil Mechanics, 2009, 30(4): 1041-1044).

Google Scholar

[4] BLOM C B M, HORST E J V, JOVANOVIC PS. Three-dimensional structural analysis of the shield-driven Green Heart, tunnel of the high-speed line south(Tunnelling and Underground Space Technology, 1999, 14(2): 217-224).

DOI: 10.1016/s0886-7798(99)00035-8

Google Scholar

[5] YE Fei. Analysis and Control for Upward Movement of Shield Tunnel During Construction( Tongji University, 2007).

Google Scholar

[6] SHEN Lin-chong,ZHONG Xiao-chun,QIN Jian-she,MIN Fan-lu. Determination of minimum thickness of overburden layer forshield tunnel through Qiantang River(Rock and Soil Mechanics, 2011,32(1): 111-116).

Google Scholar