An Extended CPM for Resource-Constrained Project Scheduling
Abstract:
In order to apply traditional CPM in resource-constrained project scheduling, the activity network is firstly formalized for resource-constrained project scheduling. Then Resource constraint in project is presented and an algorithm of the extended CPM is developed for resource-constrained project scheduling. Finally a case is conducted, which shows the accuracy and effectiveness of the extend CPM.