Mechanics Study on the Leaning-Type Arch Bridge during the Construction Process Based on Building Materials

Article Preview

Abstract:

With the constructing project of Shengli Bridge as the background, this paper presents the measured stress and deformation data of main arch rib during the process of full framing scheme. The measured data are compared with the computation results.And the mechanical behaviors of the arch bridge were studied to reveal the changing tendency of stress and displacement of the main arch construction completed to completion stage. The analysis results show that the stress and the displacement of the key structures are in a reasonable range and meet the design requirements during the process of the construction process.

You might also be interested in these eBooks

Info:

Periodical:

Pages:

166-169

Citation:

Online since:

March 2013

Export:

Price:

Permissions CCC:

Permissions PLS:

Сopyright:

© 2013 Trans Tech Publications Ltd. All Rights Reserved

Share:

Citation:

[1] JunLan-Xu. The large span bridge construction control [M]. Beijing: people's traffic press, 2000.

Google Scholar

[2] Rucheng-Xiao,Haitao-Sun,Lijun-Jia etc.Leaning type arch bridge [J]. Shanghai road press, 2004.

Google Scholar

[3] Ruisen- Zhang.Construction technology of tied arch bridge without support construction concrete filled steel tube[J]. Railway Standard Design,2005,(7):49-52.

Google Scholar

[4] Zhongquan- Zou,Guojing- He.Research on the construction monitoring of long-span CFST arch bridges[J].Journal of Central South University of Forestry&Technology,2007,(4): 71-75.

Google Scholar

[5] Yifeng-Zhong,Xuegang-Yin,Huai-Chen.Construction supervision of a long span double basket-handle arch bridge[J].Highway,2009,(1):59-62.

Google Scholar