Integration Method and Test of IEC 61850 Client in Integrated Supervision and Control System of Substation

Article Preview

Abstract:

Currently, the information exchange between various systems in substation is difficult, and the scheme of integrated supervision and control system of substation can effectively promote the smooth flow of information in the substation. In this paper, by analyzing the Communication architecture of integrated supervision and control system, the devices that communicate following the IEC61850 standard in station layer are given, which all need to integrate IEC61850 client. Then an integration method of IEC61850 client is proposed, providing unified IEC61850 client for different devices in integrated supervision and control system of substation to reduce the risk of interoperability failure because of using different IEC61850 clients. While a communication test is conducted using IED simulator and communication gateway simulator to verify the feasibility of the proposed integration method.

You might also be interested in these eBooks

Info:

Periodical:

Advanced Materials Research (Volumes 846-847)

Pages:

392-395

Citation:

Online since:

November 2013

Export:

Price:

Permissions CCC:

Permissions PLS:

Сopyright:

© 2014 Trans Tech Publications Ltd. All Rights Reserved

Share:

Citation:

* - Corresponding Author

[1] FAN Chen, NI Yimin, DOU Renhui, et al. Interpretation of relevant specifications of integrated supervision and control systems in smart substations[J]. Automation of Electric Power Systems, 2012, 36(19): 1-5.

Google Scholar

[2] Technical specifications for construction of integrated supervision and control system of smart substation. State Grid Standard Q/GDW 679, (2011).

Google Scholar

[3] Qu Zhijian, Liu Mingguang, Jiang Zhiling, et al. Study of communication gateway based on IEC61850 protocol[C], Communication Software and Networks, 2009, Page(s): 659-662.

DOI: 10.1109/iccsn.2009.17

Google Scholar

[4] Yue Fuchang, Shao Lin, Wu Zaijun. Modeling and implementation of power quality monitoring device based on IEC 61850[C]. Electricity Distribution, 2012 , Page(s): 1-5.

DOI: 10.1109/ciced.2012.6508576

Google Scholar

[5] Tan J. C, Zhang C, Bo Z.Q. The importance of IEC 61850 interoperability testing[C]. 43rd International Universities Power Engineering Conference, 2008 , Page(s): 1-5.

DOI: 10.1109/upec.2008.4651594

Google Scholar

[6] Rick Kuffel, Dean Ouellette, Paul Forsyth. Real time simulator and testing using IEC 61850[C]. Modern Electric Power Systems, 2010, Page(s): 1-8.

Google Scholar